Preliminary Airport Closing Schedule

A message from Bill Coltharp, Chairman of the Airport Advisory Board:

A preliminary schedule for closing the airport (runway and taxiways) has been determined, as required by the construction activity. Chris Robertson, Project Supervisor, Cravens Partners, is scheduling the construction activity that will require the airport to be closed beginning Tuesday morning May 27 through Friday afternoon, May 30 for the resurfacing of the runway and taxiways.

Opening for the weekend of May 31 & June 1 is possible, with NO STRIPING on the runway or taxiways.

The airport will then be closing again for two days, Monday and Tuesday, June 2 & 3 for painting the striping on all surfaces.

The airport will open again on Wednesday, June 4.

This schedule is preliminary, and is dependant on weather conditions and final approval of the engineer.

If you have any questions, please contact Bill Coltharp (bill@coltharp.com). Additional updates will be posted as they become available.